TXDOT TO BEGIN BRIDGE MAINTENANCE PROJECT ON MONDAY
The Texas Department of Transportation is set begin maintenance work this Monday on the Navasota River Bridge along State Highway 6.
The first phase of the project will include closing the outside (left) lane on State Highway 6 Northbound and the Business 6 entrance ramp to State Highway 6.
All northbound traffic on Business 6 will be detoured to the FM 3090 overpass.
The second phase will begin once Phase 1 is complete and will include repair maintenance on the State Highway 6 Southbound bridge.
Each phase is scheduled to last approximately 30 days, with the total project taking 60 days.
Schedules are dependent on weather, field conditions, and work progress.
According to TxDOT representative Bob Colwell, their construction team plans to work daily, Monday thru Sunday, until the completion of the project. Closures will be in place at all times.