CALDWELL ISD BOND LAYOUTS APPROVED
The Caldwell School District has approved the final layouts for the district’s upcoming renovations.
This past week the school board approved the final layout for a new gymnasium and career-and-technology and science building at the high school.
Among the improvements for the elementary school are, improved access and more visitor parking, improved bus access and an addition with new classrooms and a gymnasium.
The board was also informed that necessary asbestos work is being done, materials have been delivered for a new concession stand and pad work is underway for restrooms at the softball field.
The board was also informed that work has begun to repair hail damage to a number of roofs. Crews have begun replacing the roofs on the rock gym and middle school. Materials are also in place to begin work on the intermediate gym. The board was also told the high school roof still needs work.
The cost of the roof project is covered by insurance.